Mangaluru, July 24,2017: A reports informs that the run-up to produce Bharat Stage VI compliant fuel, the Mangaluru Refinery and Petrochemicals Ltd. (MRPL), is preparing to upgrade its existing production facilities as well as set up a new unit.


mrpl Catering to the fuel requirement of Karnataka and parts of neighbouring States, MRPL produces about 1.2 million tonnes per annum (MTPA) of petrol and 6.5 MTPA of BS IV standard, at present.

Having secured environment clearance from the Union Ministry of Environment, Forest and Climate Change (MoEFCC) on July 10 for the upgrade plan, MRPL will shortly commence construction activities, while project engineering work is nearly complete, said Director (Refinery) M. Venkatesh.

Conversion ability  : MRPL’s  Venkatesh said  that the company would be able to achieve the conversion of existing BS IV quality petrol and diesel facilities entirely into BS VI quality.

The conversion facilitates production of 1.2 MTPA of petrol and 7 MTPA of diesel of BS VI standard. He said the available land in the existing refinery complex would be utilised for the upgrade project by investing about Rs. 1,810 crore.

As many as 10 diesel production facilities will be upgraded and one new petrol production facility will be set up, he said.

More land needed :  For upgrading the entire diesel production capacity of the refinery into BS VI standard, MRPL requires additional processing units.

Available land within the complex is insufficient and additional land of about 1,050 acres that has been sought from the government will be required for its Phase IV expansion.

With this, another MTPA diesel production unit could be added to the existing capacity, thereby significantly contributing to BS VI diesel to Karnataka and the adjoining States, Director Venkatesh said.

While BS VI quality fuel should be available at fuel stations by April 1, 2020, the preparatory works have to start immediately.

Soon after completion of construction activities, MRPL should switch over to BS VI production by October 2019, and will start testing the products.

The new facility should be commissioned before December 2019, and production should start by January 1, 2020. Oil marketing companies will start getting supply of upgraded fuel, thereafter which it should be available in pumps from April 1, 2020.

Air pollution : BS VI norms by the Union government seek to regulate air pollutants’ output from internal combustion engines, including motor vehicles. Emission from vehicles depends on the fuel used and emission standards are prescribed to regulate the same. At present, BS IV norms are applicable across the country.

BS VI fuels come with extremely low levels of sulphur content at 10 ppm for both petrol and diesel. Sulphur is a major pollutant in vehicle exhaust emission with its oxide causing smog.

India will join the U.S., Japan and the European Union by switching over to BS VI standards, which is equivalent to Euro Stage VI.


Write Comment | E-Mail | Facebook | Twitter | Print
Error:NULL
Write your Comments on this Article
Your Name
Native Place / Place of Residence
Your E-mail
Your Comment
You have characters left.
Security Validation
Enter the characters in the image above