Flyover work at final stages near NMPT/SEZ

Flyover work at final stages near NMPT/SEZ


Mangalore Today News Network

Mangaluru, May 26, 2018: Though It’s been several years since the construction of Pumpwell flyover begun  it is still under construction, but construction work of the flyover at SEZ which began just two years back is almost complete.

 

Flyover


The special economic zone is situated close to the New Mangaluru port (NMPT). This zone has attracted national attention for the massive industries it houses and but before the massive heavy vehicle entre this zone, a corridor needs to be constructed. But, currently there exists only a mud road. Also the huge vehicles need to cross railway tracks to enter SEZ. For these reasons, a fly over has been constructed from a point close to Phalguni River to SEZ.

The construction of this fly over had begun just 2 years back at the cost of 40 crore rupees. The 700 meters long and 10.5 meters wide fly over’s construction is almost complete.

The flyover has been constructed over Jokatte railway station where the South railway division ends and the Konkan railway division begins. Presently the goods vehicles which are plying from the New Managluru Port towards SEZ have to cross the railway tracks at Jokatte railway station. Sometimes, when the trains are passing through the station, the goods vehicles have to idle on the road side for a considerable period of time. Also an alternative route was required since the huge goods vehicle found it tedious to turn near Jokatte railway crossing. To make easy movement of goods vehicle to SEZ a corridor facility needed to be created as a result the flyover was created.

 After the completion of the construction of the fly over, all the goods vehicles going towards SEZ will move through the fly over. It is being said that there is very less possibility of entry for private vehicles on this fly over. This fly over will cater to at least 100 goods vehicle daily. The fly over begins from in front of  Total gas, goes all the way to the entrance of SEZ and joins with MRPL third phase road. 

The work to be done near the railway tracks requires prior permission from the railway department receiving which the work has to be carried as per its direction. The flyover work along Jokatte region has been completed by SEZ and the remaining construction to be done above the passing railway tracks has been handed over to the railway department.    The technical department of the railway department has already begun the construction work and the money to carry the work has been handed over by SEZ. The railways have to install a 45 meter and a 18 meter span. 

 Completion within three months   “The flyover has been constructed to provide a particular corridor for goods vehicle coming towards SEZ. Already 95% of the work has been completed and the remaining work is being carried by the railways. In the next three months, vehicles will travel on this flyover,” informed senior manager (CVL) SEZ.


Write Comment | E-Mail | Facebook | Twitter | Print
Error:NULL
Write your Comments on this Article
Your Name
Native Place / Place of Residence
Your E-mail
Your Comment
You have characters left.
Security Validation
Enter the characters in the image above