‘Shiradi Ghat works’ will it be completed before monsoons


Mangalore Today News Network

Mangaluru, Mar 11, 2017: It is stated that the battered 13-km stretch between Gundia and the Kempu Hole guesthouse of Shiradi Ghat will be  motorable before the onset of monsoons in June, said Minister for Public Works, Ports and Inland Transport H.C. Mahadevappa.  Work to fill potholes on the road has already commenced: Public Works Minister


Shiradi Ghat


The minister indicated that the maintenance of Shiradi Ghat – a vital link between the coast and the hinterland – was an important work of the department. The work of filling up the potholes of the road had already commenced. Minister  Mahadevappa said that the process of calling fresh bids for reconstruction of the Shiradi Ghat road, as part of Package 2, was on. The State government had cancelled the earlier contract as the contractor did not begin the work even 13 months after issuing work orders with little delays.